SPECIAL BOARD OF ADJUSTMENT N0. 355
Parties:
STATEMENT
OF CLAIM:
FINDINGS.
Award No. 127
Case No. None
BU-4921-33
THE ORDER OF RAILROAD TELEGRAPHERS
THE BALTIMORE AND OHIO RAILROAD COMPANY
AWARD IN DOCKET NO. 127
1. Carrier violated the Agreement between the parties when
on December 23, 1957, it required or permitted an employe
not covered by said Agreement to copy a track car lineup
directly from the train dispatcher at Bond Hill, Ohio.
2. Carrier shall compensate an idle operator in the amount
of a day's pay (8 hours) on December 23, 1957.
Despite the technical points presented by the Carrier in defense, we
must conclude there were three operator - QS - positions at Bond Hill (they are so
listed in the agreement reprint) and the claim will be sustained,
A W A R D
Claim sustained.
/s/R. K. Anthis
R. K. Anthis
Employee Member
Dated at Baltimore, Maryland
this 31st day of May, 1963.
/s/Edward A. Lynch
Edward A. Lynch, Chairman
/s/T. S. Woods
T. S. Woods
Carrier Member