SPECIAL BOARD OF ADJUSTMENT N0. 506
THE ORDER OF RAILROAD TELEGRAPHERS
VS.
MISSOURI PACIFIC RAILROAD COMPANY
Roy R. Ray, Referee
STATEMENT OF CLAIM:
"Claim of the General Committee of The Order of Railroad Telegraphers on the Missouri
Pacific Railroad (Gulf District) that:
Claim No. 1
1. Carrier violated Vacation Agreement on June 19, 1961, when it
canceled C. W. Plummer's scheduled vacation beginning June 22, 1961.
2. Carrier shall compensate C. W. Plummer an additional eight (8) hours
at time and one-half rate for each day, June 22, 1961 through and
including July 10, 1961, his scheduled vacation.
Claim No. 2
1. Carrier violated Vacation Agreement on July 5, 1961, when it cancelled
W. F. Bradley's vacation beginning July 11, 1961.
2. Carrier shall compensate W. F. Bradley an additional eight (8) hours
at time and one-half rate for each day, July 11, 1961 through and including July 22, 1961, his scheduled vacation."
OPINION OF BOARD:
Claimant Plummer, a regular telegrapher in the Palestine, Texas, Relay Office
had been assigned a vacation period from June 22 to July 10, 1961. On June 19th,
three days before it was to begin, he was notified by Carrier that his vacation
would be postponed because no vacation relief was available to relieve him. Claimant Plummer worked the entire period of his scheduled vacation. He was later
assigned another vacation period beginning August 4, 1961, which he took.
Claimant Bradley, a regular telegrapher in the Palestine, Texas, Relay Office
had been assigned a vacation period from July 11 to July 22, 1961. On July 5th,
six days before it was to begin, he was notified by Carrier that his vacation would
be postponed because no qualified operator was available to relieve him. Claimant
Bradley was later assigned another vacation period beginning July 18, 1961, which
he took.
In each case claim was made for compensation at the time and one-half rate
for each day of the scheduled vacation. Employes contend that Carrier violated
Article V of the Vacation Agreement (1941) as amended by Article I, Section 4 of
the 1954 Agreement when it deferred the vacation of Claimants without giving them
_~-G A
5n(o 0 !
AWARD N0. 15
DOCIKE,T N0. 15
ORT CASE N0. 3593 PAGE 2
the required ten (10) days' notice. These provisions are set forth in the submissions and it is not uecessary.to repeat them there. Under Article V Carrier is
authorized to defer vacations but must_give at least 10 days' notice unless
emergency conditions prevent.
Carrier contends that the shortage of extra telegraphers to fill the positions of Claimants at the time of the scheduled vacations constituted emergency
conditions relieving Carrier of its obligation to give the 10 days' notice.
The chief issue before the Board is whether the situations which existed
at the times in question can be classed as emergency conditions. In its submission
Carrier says that arrangements had been made for Extra Telegrapher Davidson to
relieve Claimants during their scheduled vacations. But that on June 19th and again
on July 5th, he was called into the Dispatcher°s office to provide relief there and
thus was unavailable to relieve Plummer on June 22nd and Bradley on July 11th; that
since Carrier had no one else available to relieve Claimants it had no choice but
to postpone their vacations, Carrier claims that it normally has two extra telegraphers to perform relief service at Palestine.
Although not mentioned in the handling on the property, at the hearing before
the Board Carrier stated that the other extra employe it had counted upon for
relief was Mrs. Russell. But that on June 14 she was permitted to fill a vacancy
on the line leaving only Davidson available, that on June 19 when he was called to
Dispatcher's Office to provide relief there, the Superintendent of Communications
tried to get Mrs. Russell back but was unable to do so. As to Claim No. 2, Carrier
said it tried to get Mrs. Russell back to relieve Bradley but could not do so. It
then arranged to have Telegrapher Slay relieve Bradley but on July 5 he became ill
and Carrier had no other employe available.
Under Carrier's own admission the only relief it had planned to protect
vacations of the two Claimants were Russell and Davidson. At the hearing it was
brought out that Mrs. Russell could not be relied upon since she was called upon
frequently to protect other assignments. In our view the situation which arose
cannot be classed as an emergency. It was not an unforeseeable combination of
circumstances. With only two extra telegraphers in sight to protect these vacations,
one or both of whom was subject to call to protect other positions, Carrier should
certainly have realized that this was an inadequate force at the time of year when
there is a heavy vacation schedule.
In two recent awards the Third Division has held that the shortage of extra
telegraphers for vacation relief does not constitute an emergency. Awards 10839 and
10919. These awards on similar fact situations are persuasive here. We hold therefore that Carrier violated the Agreement in deferring the vacations of Claimants
without proper notice.
As to the matter of compensation, Carrier argues that Claimants are not
entitled to any compensation beyond what they have already received. It contends
that Section 4 of the 1954 Amendment to Vacation Agreement does not apply because
Claimants were later given vacations. We reject this line of reasoning as unsound.
In this connection we quote from Award 10839 of the Third Division on the same
point:
.
Sb ~s ~ Dh
AWARD N0. 15
DOCKET N0. 15
ORT CASE N0. 3593 PAGE 3
"If this line of reasoning were accepted, we would have a wrong
without a remedy. If Carrier can postpone an employe's scheduled
vacation at will without any proper notice where no emergency exists
without incurring any liability and force employe to take his vacation at some later time, Article 5 would be meaningless and the employe would have no security whatever in his assigned vacation. In
our view this is contrary to the spirit as well as the language of
the Agreement."
In the instant case Carrier has deferred Claimant's vacations without
adequate notice and it becomes obligated to compensate them for the vacations at
the regular rate and to pay them at the time and one-half rate for the periods
they worked during their scheduled vacations. Since Claimant Plummer worked the
entire period, he is to be paid for all of it. Since Claimant Bradley worked
only a week of his scheduled vacation, his compensation is to be limited to this
period.
FINDINGS: That the Agreement was violated.
AWARD
Claims sustained to the extent indicated in the Opinion.
SPECIAL BOARD OF ADJUSTMENT N0. 506
/s/ Roy R. Ray
Roy R. Ray - Chairman
/s/ D. A. Bobo /s/ G. W. Johnson
D. A. Bobo - Employe Member G. W. Johnson-Carrier Member
Dissent Attached -
St. Louis, Missouri'
August 20, 1963
File 279-195
279-199
s('~i~
`c(o
-/dwD
~5
CARRIER MEMBER'S DISSENT TO AWARD N0. 15
SPECIAL BOARD OF ADJUSTMENT N0. 506
(O.R.T. versus Mo.Pac.RR)
Award No. 15 is in error because the majority
1. Disregarded the facts in concluding that no emergency conditions
existed, and
2. Exceeded its authority by assessing a penalty not provided for in
the effective Agreement.
1. The facts of record show that vacations were duly scheduled for Claimants
Plummer and Bradley, and that extra telegraphers were available to relieve the
claimants for vacations as scheduled until June 19, 1961, in "Claim No. 1," and
until July 5, 1961, in "Claim No. 2." On those dates the two extra telegraphers
relied upon by the Carrier to relieve the claimants for vacations became unavailable by reason of their exercise of seniority to other prior vacancies or by
reason of illness. In view of the needs of the service, claimants' positions
could not be blanked during the period for which their vacations had been scheduled,
and they were notified of the deferment of their vacations on June 19, 1961, and
on July 5, 1961, respectively.
Both claimants were compensated at the pro rata rate for days worked during
the period for which vacations were originally scheduled. Vacations for both
claimants were rescheduled promptly and Claimant Plummer took his vacation
beginning August 4, 1961, and Claimant Bradley took his vacation beginning
July 18, 1961, and both were compensated at the pro rata rate while on vacation.
Article 5 of the Vacation Agreement of 1941 provides, in part, as follows:
" *%'-` the management shall have the right to defer (vacations)
provided the employee so affected is given as much advance notice
as possible; not less than ten (10) days' notice shall be given
except when emergency conditions prevent."
The Carrier recognizes that the purpose and intent of the Vacation Agreement
is to provide vacations with pay to employes who qualify therefor, and the Third
Division of the National Railroad Adjustment Board has so held. See Award No.
10958 (Dolnick) which held that -
" *:* It is a fundamental principle that the purpose of the Vacation
Agreement is to provide time off, not pay. ''%*·* If an employe is
unwilling to co-operate and agree on a vacation date, it is the duty
of the Carrier to set the vacation period within the year when it is
earned. ' ··*%~ %~*."
When emergency conditions arose less than ten (10) days prior to date
vacations were scheduled to begin, the Carrier gave as much notice as possible
of the deferment, and promptly rescheduled them, at which time relief workers
were available, and the claimants were accorded vacations with pay. Thus, the
Carrier complied with the intent, purpose and language of the Vacation Agreement;
particularly Article 5 thereof; but for doing so it has been found by the
majority to be in violation of the Vacation Agreement:'.
~ `JOIo ~ Hw O l ~
During the hearings before the Board copies of Award No. 17, Special Board
of Adjustment No. 305 (O.R.T. vs Mo.Pac.), Referee McMahon, and Award No. 22,
Special Board of Adjustment No. 166 (BRC vs Mo.Pac.). Referee L. Smith, were
made available to the Board. Both of these awards denied claims for additional
compensation in behalf of claimants whose vacations had been deferred with less
than ten (10) days' notice on the grounds of emergency occasioned by the illness
of the extra employes relied upon by the Carrier to relieve the vacationing
employes there involved. In those cases, as here, vacations were rescheduled,
which the employes took with pay.
To the same effect, see Third Division (Supp.) Awards Nos. 10357 (Referee
Schedler), and 10965 (Referee Dorsey), and Third Division Award No. 10958
(Referee Dolnick).
2. After having erroneously concluded no emergency conditions existed, the
majority was then unable to find a rule in any Agreement between the parties which
would support claims for additional compensation at the punitive rate of time and
one-half for days worked (for which they were compensated at the pro rata rate)
during the period for which vacations were originally scheduled; it being undisputed that both claimants took their rescheduled vacations with pay, and without
protest.
On page 1 of this Dissent we quoted a portion of Article 5 of the Vacation
Agreement of 1941 with respect to the right of the Carrier to defer vacations.
The last paragraph reads as follows:
"If a carrier finds that it cannot release an employee for a vacation
during the calendar year because of the requirements of the service,
then such employee shall be paid in lieu of the vacation the allowance hereinafter provided."
The "allowance hereinafter provided,'1 referred to in Article 5, is found in Article
7 of said Agreement. Article 5 of the Vacation Agreement of 1941 was amended by
Article I, Section 4 of the National Non-Op Agreement of August 21, 1954, as follows:
"Effective January 1, 1955, Article 5 of the Vacation Agreement of
December 17, 1941 is hereby amended by adding the following:
Such employee shall be paid the time and one=half rate for work
performed during his vacation period in addition to his regular
vacation pay."
The application of the language of amending Article I, Section 4, quoted
above, has been interpreted by Third Division Award No. 8282 (Referee Lynch) as
follows:
"It is perfectly clear that 'such employe', referred to in the quoted
amendment means the employe Carrier was unable to release at any time
during the year for vacation because of the requirements of the service."
(Emphasis supplied.)
The same language of the 1954 Amendment was again interpreted by Third
Division Award No. 9228 (Referee Rose) as follows:
The sole question presented is whether the provisions of the
Amendment quoted above entitle Claimant to the time and one-half rate
because his vacation period, originally scheduled to begin on June 13,
1955, was deferred to the month of September, 1955.
-2-
_ 0
S 6- ~o(~ - ~aW
D
l5
"The answer to this question must be in the negative. It is entirely
clear that the words 'such employe' in the Amendment mean 'an employe'
who cannot be released by the Carrier 'for a vacation during the calendar year because of the requirements of the service' as stated in
Article 5. (Award 8282.)"
Again, Third Division Award No. 7820 (Referee Smith), as follows:
"Article 5 of the National Vacation Agreement covers two existing conditions, namely, when vacations are taken and when they are not taken.
The sole penalty provided when employes are net permitted to take
their vacation is payment in lieu thereof. Claimant here was so
compensated." (Emphasis supplied.)
It is abundantly clear from the awards cited and quoted in part abcve that
the penalty provided by the parties in negotiated agreements applies only to
those employes the Carrier is unable to release for vacations during the calendar
year, and to no other. Since the claimants here HERE released for vacations
during the calendar year 1961, which both took without protest and with pay,
there can be no Agreement support for the award of the majority here.
Special Board of Adjustment No. 506 was established by Agreement between the
Mo. Pac. RR Company and the O.R.T., dated April 10, 1963, paragraph H of which
reads as follows:
"The Board shall not have jurisdiction of disputes growing out of
request for change in rates of pay, rules and working conditions,
and shall not have authority to change existing agreements governing
rates of pay, rules and working conditions."
The foreoing language specifically prohibits the changing of existing Agreements or the writing of new rules under the guise of interpretation, administering
equity, or otherwise. The authority of this Board is limited by Agreement to
interpreting existing Agreements. As has been seen, the language of Article 5 of
the Vacation Agreement of December 17, 1941, as amended by Article I, Section 4
of the National Non-Op Agreement of August 21, 1954, does not and cannot support
an interpretation which extends the specific penalty provided for therein to include employes who are released for a vacation during the calendar year, with pay.
Awards Nos. 8282 (Lynch), 9228 (Rose), 7820 (Smith), have refused to extend the
penalty in Article 5 as has been done here.
While some awards of the Third Division, National Railroad Adjustment Board,
have assessed penalties where none is provided in applicable Agreements, there is
no authority for doing so to be found in its creator, the Railway Labor Act, and
numerous awards of all Divisions of the N.R.A.B. have so held.
Third Division Award No. 10511 held to this effect in the following language:
"**** It is not the function of the Board, however, to indiscriminately
assess punitive damages where no fraud, no discrimination or no malice
is shown in the record and where no employe, whether it be the proper
Claimant or not, had suffered or may have suffered any damages by reason
of such alleged violation.
"It is a fundamental principle of law that damages for a breach of contract
is the amount which the Claimant actually suffered by reason of such a
breach.
S 6~ ~h - ~9~.m
o
15
As stated in Third Division Award No. 8673
'Punitive damages are not ordinarily approved by the Board.'
To the same effect see Awards Nos. 3651 (Miller), 5186 (Boyd), 7309(Rader) and
8674 (Vokoun).
Again, in Award No. 10963, Third Division, (Referee Dorsey), the Board,
in refusing to assess penalty, held as follows:
"* * * Therefore, for this Board to make an Award as prayed for in
Parts-(2) and (3) of the Claim would be imposing a penalty on the
Carrier and giving the MW Employes a windfall m-neither of such
results is provided for or contemplated by the terms of the contract.
To make such an Award, we find, would be beyond the jurisdiction of
this Board."
Once more, in Third Division Award No. 7309, the Board held:
"*** The assessing of the penalty claim would be an extremely drastic
measure to be invoked and one of doubtful legality under the rules of
the Agreement, as no specific rule can be used as a basis for such
an award."
Finally, in Third Division (Supplemental) Award No. 10965 (Referee Dorsey)
the Board held, in a case similar to the instant dispute-
"The Claim must be denied for still another reason. Claimant did,
without protest, take his vacation as reassigned and was paid in
accordance with the terms of the Agreement. While Claimant may have
been inconvenienced by the deferment, he suffered no loss of wages.
The Agreement does not provide for compensatory damages for inconvenience."
In any event, as we have seen, the creators of Board No. 506 specifically
provided by Agreement that it "shall not have authority to change existing Agreements governing rates of pay, rules and working conditions." Yet that is the
effect of this Award No. 15, if it is to be regarded as a precedent. All this to
the injury of one party, the Missouri Pacific Railroad Company, to the unjust
enrichment of the claimants, and to the injury of other employes who desire a
vacation with pay, even if their duly scheduled vacations must be deferred with
less than ten (10) days' notice, as here, in order to accomplish that result.
For these reasons, I dissent.
/s/ G. W. Johnson
G. W. Johnson - Carrier Member
St. Louis, Missouri
September 5, 1963