z ° ~S
MAY 81964
SPECIAL BOARD OF ADJUSTMENT N0. 525'~i.'-_~,x~ j
AWARD N0. 28
CASE N0. 28
k
GRAND DIV.: BU-8751-49 -
ORGANIZATION FILE
: CARRIER FILE:
R-1321 TE-17-63
1. (A) Carrier violated the Telegraphers' Agreement on
March 31, 1963, when it required and permitted Conductor on work extra 5952 to copy a train order for
his train at M.P. 186.36.
(B) Carrier violated the Telegraphers' Agreement on
March 31, 1963, when it required and permitted Conductor on train No. 9 to copy a train order for his
train at Sidney.
2. (A) Carrier. shall compensate the senior idle extra
Telegrapher with less than 40 hours work in his work
week and in the event there are no idle extra Teleg-
raphers with less than 40 hours work in their work'
week, carrier shall compensate the senior regular as-
signed man off on rest day, for one day's pay (8 hours) `
for the violation claimed in 1. (A).
F
(B) Carrier shall compensate the senior idle extra
Telegrapher with less than 40 hours work in his work
week and in the event there are no idle extra Telegraphers with less than 40 hours work in their work
week, Carrier shall compensate the senior regular
assigned man off on rest day, for one days pay
(8 hours) for the violation claimed in 1. (B)."
SPECIFIC FINDINGS
:
On Sunday, March 31, 1963, at 12:30 A.M. three pilings were
i
washed out from bridge 187.94 two miles east of Steamboat Springs by
G
ice jam. A pile driver was called out of Denver at 4:00 A.M. and
departed Phippsburg as Work
Extra 5952 at 1:40 P.M. to repair damage.
cep ~~s
-Awo z8
:.'he pile driver arrived at bridge at 2:10 P.M., drove two temporary
pilings. The bridge was safe for traffic at 10:05 P.M. Train No. 10
was first over bridge at 10:27 P.M. - 1312411 late. No. 9 departed
Phippsburg at 6:20 P.M. 3T52" late and was delayed at Sidney 314011
meeting No. 10.
Conductor on Work 'bKtra 5952 copied train order No. 20 at 9:05 P.M.
at Mile Post 186.36 which is 4.74 miles east of Steamboat Springs where
there is an agent employed but not on duty.' At 9:12 P.M. March 31,
1963, conductor on train No. 9 copied train order at Sidney, 7.4 miles i
i
east of Steamboat Springs. Claim for eight hours was denied.
It is Carriers first-position that this was an emergency under
a provision of Rule 21(0)2. It also defends on the grounds that a
specific claimant was not named. - _ -
The Organization denied that an emergency existed and contends
that because the work was not performed at a station where employes i
' a
are employed, it does not fall under provisions of Rule 6( M) as the
Carrier contends, nor under the Call rule. The Organization asserts
that Rule 6M "Work on Unassigned Days -" refers to work performed on
the unfilled days of a regular assignment, for instance, the sixth and
seventh day of a five-day assignment.
We are not persuaded by the Carrier's strict construction of
s
4
Rule 21(0)2 defining "emergency," nor do we feel compelled to follow
Award 6639 in its parsing of the defining sentence. Webster defines
emergency as,
ttan
unforeseen combination of circumstances which calls .
for immediate action." The rule names a number of examples followed
4
v
-.2 - '
r f
i1·'
by a general catch-all phrase, "other unforeseen occurrences," and
concludes, Ihahich could not have been anticipated when train was at previous
open telegraph office, etc." This latter phrase, we find, applies to
the occurrences contemplated in the entire paragraph, otherwise we
pass completely beyond a reasonable and ordinary
meaning of
an emergency.
(Quite aside, we do notice a semi-colon in 1st Division Award No. 1+951,
cited by Carrier, which is not present in our Rule). The facts before
us, with long time spreads, do not spell out an emergency.
The remaining question concerns compensation. The National
Railroad Adjustment Hoard has ruled in numerous cases that a claimant
need not-be named so long as he can be identified.
The instant work was improperly performed by the conductors
and Rule ?1 was violated. Assuming, as Carrier contends, that the
work could have been performed by the telegrapher at Steamboat on a
single call, the Carrier did not proceed in that manner. We are con6erned with a penalty day and the Organization must determine which o4-8f the two claimants-shall-receive it
as
we do not grant double penalties.
--AWE __
Claim sustained per Findings, supra.
SPECIAL HOARD OF ADJUSTMENT N0. 525
Denver, Colorado (Signed) J. Glenn Donaldson
March 7;?, 1961+ J. Glenn Donaldson, Neutral Member
Chairman
(Signed) R. K. Anthis
R. K. Anthis, Organization Member
(Signed) C. E. Baldridge - Dissent
C. E. Haldridge, Carrier.Meiaber
-3-