' S.H.A. Ho. 570
' Award Ho. 312
( Case Ho. 358
SPECIAL BOARD OF- aD.nrUT1=tT N0. 570
- Established Under'
Agreement of September 25, 19511
Chicago, Illinois - September 28, 1972
PARTIES System Federation No. 22
TO Railway Employes' Department, AFofL-CIO
DIP=:
(Sheet Metal Workers)
Va.
St. Louis-San Francisco Railway Company
STATFt~,?fT 1. That the St. Louis-San Francisco Railway Compeay
OF CLAIM: violated the Agreement of September 25,
1954
when -
(a) They improperly contracted out the work of
. manufacturing of air conditioning and heat
ing ducts end installing same in office
building at Enid, Oklahoma to the Western
Sheet Metal Compares, Enid , 0:%lahoma on cr
. about November 18, 1970, through December 1,
1970, which was is violation of Article II
of the Agreement.
(b) They did not give the emple._·es any advance
notice in violation of Article I Section 4
and Article II Section 2 of the Agreement.
(c) That accordingly, the St. Louis-San Francisco
Railway CompwW be ordered to c=pensate the
following Sheat Metal Water, Service men time
and one-half for the same .:mount of hours paid
for labor by the Western Sheet Metal. Compazzy
at Enid, Oylahcma: _
_ _ . S.B.A. No.
570 '
Award No. 312
- 2 - Case Ho. 368
Edwin Jones ' D. 0. Woods .
Heil Davis T. S. Watson.
Of the above named Claimants, T. S. Watson
is a furloughed Water Service man from '
Oklehoma City, Oklahoma. - ,
DISCUSSIOa At issue in this case is the alleged impropriety on '
AND Carrier's tart in delegating to Glen 'Katson d/b/a
FTfDIHGS: Western Sheet Metal Co., Fnid, Okla., the manufacture
and installation of air conditioning and heating ducts .
amounting to $2,872.00 (the same being, cue portion of the Job assigned
to the outside ccntrcctor to furnish all materials, equipment and labor
for a complete heating and air Conditioning system at an estimated price
of $6,124.84) for use in the prefabricated metal office and wash-locker
building to be constructed on Carrier's property at Enid, Okla. at a cost
of approximately
$66,500.00. -
The principle that Carrier is not required by the Agreement
of September 25, 1964, to break doaa the heating and air conditioning
project into its cc=pcnent parts so as to permit the handling on the
property by the Water Service fochanics and Helpers of the related duct
work, has been laid down by this Board. Sao Awards Numbered 228, 295,
299 and 309, Special Board of Adjustment No. 570.
Noticeably, three of the four claimants herein were regularly'
assigned as full ti=e Water Service N.echanics throughout November and
December, 1970, the period durin.3 which the heating and air conditioning
contract was acccrplished. Tney did not suffer any ware los: as a doaaequence of the contracting cut, and under Article PI, Section 14 of the
September
25, 1564
Agreement, they are precluded frca-obtaining a monetary
award. See Awards numbered 8, 44,
53
and
309s
Special Board of Adjustment
No- 570,.
.. The fourth claimant, T. S. Watson,
although on
furlough
for the two months of November and December, 1970, has no basis for
=plaint since, in the instant case, a violation of the September
25,
1964
Agreement .is not proved. . . ..
' . AWAF81: Claim denib&. . , . . ' . '
- $.B.A. No. 570
Award No. 312
3
- Case 11o.
368
I
Adopted at Chicago, Illinois - September 23, 1972.
Harold td. Gilden - Neutral Member
.
~7c~ - _. .-
e ,
Caz-rier Members Dnloye Mem ^r s