S.B.A. 140. 570
AWARD NO. 488
 
CASE N0. 572
SPECIAL BOARD OF ADJUST:-_MT 110. 570
ESTABLISHED UNDER
AGR=·tEiT OF SEPTZ_?3ER 25, 
1964
Chicago, Illinois - J
VNZZ 
.24, I`Tfho
PARTIES
 
_TO
DISSPU7"E:
System Federation No. 1, Railway Employes'
Department - A. F. of L. - C. I. 0.
 
Electrical "orkers
and
Consolidated Pail Corporation
STATZ~EENT "1. That the Consolidated Rail Corporation (Conrail) violated
OF CLAZd: the Controlling Agreement of System Federation 103, the
 
Mediation Agreement of September 25, 
1954, 
Article II,
 
Section 1, 2, 3, and 
4 
when it improperly contracted out
 
the work of the electrical craft, as outlined in Rule 
140
 
of the Controlling Agreement, to an outside contractor at
 
Mound Road Yard, Michigan.
"2. That, accordingly, the Carrier be ordered to compensate
 
Electricians J. Kochan, T. Hayman, D. Parish and D.
 
Zellerino to amount of monies that they would have earned
 
had they not been deprived of their contractual rights to
 
perform the work granted to an outside contractor."
OPINION On Yarch 27, 1978, Carrier informed the General Chairman that it in
 
AND tended to subcontract the construction of a 
44' 
x 50' one-story
FIaDI:1GS: concrete block yard office building at the Mound Road Yard in Warren,
 
Michigar. The estimated cost of the project was $30,000 -- $23,C00
 
for electrical work and -$20,CO0 for sheet metal work. Carrier con
tends that the sc)ccn'1:octia.-~ c: this pro_ect was done in accordance wit!: its
_ 2 _ S.B.A. NO- 570
YARD f0. 
438
 
CASE f0. 572
right to do so under the September 25, 
1964 
Agreement. Petitioner alleges
otherwise and, by letter dated Octcber 13, 1973, filed the instant claim.
Carrier contends that the claim rams untimely filed and should be
dismissed. This Board, in a long lire of awards on timeliness, has ruled that
the st&ndard time limit rule does not apply to problems of emDloyee protection
and subcontracting covered under the September 25, 
1964 
Agreement. We so rule
in this instance.
As to the merits of this case, this Board has often co.Tented on
the points raised by Carrier and has upheld many clairs based on the same or
similar arguments as are proffered by Carrier in this case.
This Board has generally held in cases involving the construction
of new facilities that Carriers are not obligated to piecemeal the contract
to permit the assignment of a part of the work to Carrier's employees. We have
stated our rationale for this concept in numerous awards. For example, see a
recent decision, Award So. 
433, 
that cites further cases in support of the
Board's position.
To further support Carrier's position in this instance, Carrier
argued local ordinances required that licensed personnel and a resgistered
contractor were required in order to do construction in the city of Warren.
Carrier says it does not employ licensed employees, such as were required,
nor is it a registered electrical contractor. These assertions were not ref uted by tt-- employees during the handling of this case on the property.
Based on these facts, it is clear that Carrier did not violate the Agreement
when it subcontracted for the building involved in this dispute.
This Board, after consideration of the disi,ute identified above,
hereby orders that an Award favorable to the Petitioner should not be made.
The claim is disposed of as set forth in the foregoing.
A W A R D
Claim denied.
Adopted at Chicago, Illinois, 
;z
R dney E. Dennis - Neutral Member
Carrier Members
S.B.A. N0. 570
 
AWARD N0. 483
  
CASE N0. 
572