RAL Harper
s.B.A. No.
570
Award No.
53
Case
62
Special Board of Adjustment No.
570
Established Under
Agreement of September
25, 1964
Chicago, Illinois - July
20, 1967
PARTIES System Federation No.
25
TO Railway Employes' Department
DISPUTE: AFL-CIO, Machinists
and
Terminal Railroad Association of St. Louis
STATEN~_NT 1. That the Terminal Railroad Association of St. Louis violated
OF CLAIM: Article II of the September
25, 1964
Agreerent when it sent
Ballast Regulator T.R.R.A. No.
145
off the property for re
pairs and further violated the Agreement when it failed to
give advance notice and the reasons therefor, together with
supporting data.
2.- That accordingly, the Terminal Railroad Association of
St. Louis compensate the Machinists in the amount of eight
(8)
hours each at the overtime rate for the days appearing
next to their names account they were available and should
have been called to perform this work.
NAME DATE AMT. OF TIME CLAIMED
De Allyon Sloan May
24, 1965 8
hrs. at overtime rate
William Marquis May
24, 1965 8
hrs. at overtime rate
FINDINGS: Carrier leased Ballast Regulator T.R.R.A. No.
145
to Missouri
Pacific Railroad in
1963
and it was returned to Carrier on
April 12,
1965·
On May
21, 1965,
Carrier sent the equipment
in question to Railroad Machinery Service Corporation in Brooklyn, Illinois
for repairs.
Under terms of the lease, Missouri Pacific Railroad agreed to
be responsible for all repairs and was to return the Regulator in as good condition as when delivered, normal wear excented. When the equipment was returned to Carrier, it was not in as good condition as when delivered and Missouri
Pacific acknowledged responsibility.
Carrier's position is that the repair work performed on the machine
was the sole responsibility of the Missouri Pacific Railroad under the terms of
the lease between Carrier and said Railroad; that the work did not develop as a
result of use of the machine by Carrier's employes. Carrier further asserts
that Missouri Pacific Railroad requested Carrier to send the Regulator to Railroad Machinery Corporation to be repaired at said Railroad's expense.
_ 2 - 5,6
A5-7o - ,a-w
0
53
The Organization's position is that work performed by the outside
contractor is work covered by Rule 52 and also work of a type currently performed by Carrier's employes. The Organization further argues that the lease
itself did not exclude the work from being performed by Carrier's employes.
We do not agree with Carrier that the lease relieves Carrier from
any possible violation of the September 25,
1964
Agreement. The facts show
that Carrier had the option of returning the Regulator to the Missouri Pacific
Railroad in order for said Railroad to have the necessary repair work performed
in accordance with the lease. However, Carrier in this instance, chose to
take it upon itself the ,job of having the repairs completed. When it did this
regardless of whether tie Missouri Pacific Railroad directed it to send it to
a named outside contractor, it undertook the making of the repairs to this
equipment and thereby subjected itself to any possible violation of the Agreement with the Organization in regard to Article II, Subcontracting.
Carrier has raised a procedural defect, alleging that claimants
were not specifically named within sixty days of the date of the filing of
the claim and thus did not conform to the requirements of the Memorandum of
Understanding of January
7, 1965
between the parties hereto. In reply to
this position, the Organization alleges that it complied with the Memorandum
of Understanding of January
7, 1965.
Examination of said Memorandum of
Understanding reveals that disputes processed to this Board are not subject to
the provisions of the standard Time Limit Rule, and further the agreement
reads: "If the alleged violation of Article II - Subcontracting, is then
submitted-.to the Shop Craft Special Board of Adjustment, it will be considered
that the special procedural provisions of Article VI have been complied with."
Therefore, we must reject Carrier's contention in regard to its allegation
of said procedural defect.
In regard to the merits of this claim, Carrier bases its defense
solely on the contention of non-responsibility due to the lease provisions
with the Missouri Pacific Railroad in regard to this equipment. Nowhere in
the record does Carrier allege that it did not have on the property the
necessary managerial skills, skilled manpower or essential equipment available
to do this work. Therefore, we must conclude that the repairs herein involved
come within the limitation of the Carrier to subcontract this work as set
forth in Article II, Section 1, thereof. Further, Carrier failed to furnish
the Organization with advance notice of intent to contract out the work herein
and the reasons therefor, together with supporting data, as required by Section
2 of Article II, although Carrier eventually did comply with Section 3 by
furnishing sufficient data to the General Chairman.
There was no evidence submitted as to any pecuniary loss to the
claimants herein. The Organization however says that based on the experience
of the machinist claimants, they estimate that approximately
16
hours of labor
were used to make the repairs a.na thus were entitled to
8
hours each at the
overtime rate for the 2 claimants, although claimants did not suffer any wage
loss due to the subcontracting of this work.
Section 14 of Article VI clearly limits the Dower of this Board
in regard to a claim for wage loss arising out of an alleged violation of
Article II, Subcontracting, namely: ". . . the Board's decision shall not ,
S.Ql~
X70
- A-uD
exceed wages lost and other benefits necessary to make the employee whole."
Therefore, there being no wages lost, the claim for compensation in this instance must be denied.
A W A R D
Claim sustained with reference to the violation of Sections 1 and
2 of Article II of the
1964
Agreement, and denied otherwise.
Adopted at Chicago, Illinois, July 20,
1967.
Neutral Member
Carrier Memb rs Employe Members
t (. '
c v ~t
..c.w
;u_.T
~~
, r<,i z ~.1 C~.:;:. r-f-
Cy
Q,2e . °~--~i- ,~.--e-_-~1~
.