SPECIAL BOARD OF ADJUSTMENT NO. 894
BROTHERHOOD OF LOCOMOTIVE ENGINEERS
"Organization"
VS.
CONSOLIDATED RAIL CORPORATION
"Carrier"
STATEMENT OF CLAIM
Case No. 1412
Award No. 1412
System Docket CRE-11821
Claim of Engineer J. E. Adimey for payment of one (1)
hour and five (5) minutes additional Final Terminal
Delay (FTD) payment while covering Train OPSE-8 on
March 8, 1988 in accordance with Article R-c-2.
OPINION OF THE BOARD
On the date of claim, Claimant was the engineer on train
OPSE-8 operating in through freight service from Oak Point, New
York to Selkirk, New York. On his time card for the day,
Claimant reported his engine reaching the final terminal delay
point, CP-SK, at 5:50 a.m. According to Carrier, Claimant's
train arrived at the advanced signal governing movement to CP-SK
at 5:50 a.m., but did not actually pass through CP-SK until 8:11
a.m. Claimant signed off duty at 8:30 a.m. Claimant then
submitted a claim for one hour forty minutes final terminal delay
payment. Carrier ultimately granted Claimant payment of 35
minutes final terminal delay,
remainder one hour and five minutes.
but denied the
claim for the
The Organization then
S&P,
,t,~.. ~~t~l -Awes ~. lYld
placed that portion of the claim before this Board.
Article R-c-2, Final Terminal Delay of the Agreement states
in part as follows:
(a) In freight service, final terminal delay shall be
computed from time engine reaches the designated main
track switch connection with the yard track or signal
governing such connection to time of arrival at point
of final release; and for following freight trains
destined to that yard when held within yard limits by
such preceding train. After the lapse of 1 hour, final
terminal delay shall be paid for on the minute basis at
the regular hourly rate, according to weight of engine
on drivers, up to the period when overtime commences;
time thereafter shall be paid for as overtime.
Question and Answer No. 1 of the agreed to Questions
and Answers for Article R-c-2 states:
1. Question - Re (a). What is intended by the phrase
"and for following freight trains destined to that yard
when held by such preceding train"?
Answer - This means that should trains be held by
a preceding train which has reached the designated main
track switch connection with the yard track or signal
governing such connection, final terminal delay shall
be computed for the following freight trains after the
lapse of one hour from the time held. However, trains
held for any other reason would not qualify for final
terminal delay.
Article V - Final Terminal Delay, Freight Service of Award
of Arbitration Board No. 458 states in part as follows:.
Section 1 - Computation of Time
In freight service all time, in excess of 60 minutes,
computed from the time engine reaches switch, or signal
governing same, used in entering final terminal yard
where train is to be left or yarded, until finally
relieved from duty, shall be paid for as final terminal
delay; provided, that if a train is deliberately
delayed between the last siding or station and such
switch or signal, the time held at such point will be
added to any time calculated as final terminal delay.
2
584 ~'e. 8'?4 -Awo .uo- t
Yla
In addition, Letter 3A concerning Section 1 of Arbitration
Board No. 458 states as follows:
On the other hand, the Carriers were concerned that the
term "deliberately delayed" not be construed in such a
manner as to include time when crews were held between
the last siding or station and the point where final
terminal delay begins because of typical railroad
operations, emergency conditions, or appropriate
managerial decisions. A number of examples were cited
including, among others, situations where a train is
stopped; to allow another train to run around it; for a
crew to check for hot boxes or defective equipment; for
a crew to switch a plant; at a red signal (except if
stopped because of a preceding train which has arrived
at final terminal delay point and is on final terminal
time, the time of .such delay by the crew so stopped
will be calculated as final terminal delay); because of
track or signal maintenance or construction work; to
allow an outbound train to come out of the yard; and
because of a derailment inside the yard which prevents
the train held from being yarded on the desired track,
e.g., the receiving track. We agreed that Section 1
did not comprehend such conditions.
The Organization contends that as Claimant's train was at
CP-SK at 5:50 a.m., and was held behind other trains, he is
t to the
asserts
alleged
trains
on asserts
n or the
outbound
and there
was simply no room in Selkirk Yard for receiving the inbound
trains.
Carrier asserts that as Claimant's train had not actually
e
il
entitled to the final terminal delay sought pursuant
provisions of Article R-c-2. Moreover, the organization
that Carrier has never provided it with a copy of th records demonstrating that train OPSE-8 !'was held unt TV-19 and TV-8B departed Selkirk Yard."
that these trains had no bearing on
preceding trains that were stopped in
trains depart via a -different yard than inbound trains,
The organization
Claimant's train
front of it, as
58,4 No. gr4 -Aw4 .vo ~IYI~
reached the final terminal delay point of CP-SK until 8:11 a.m.,
the provisions of Article V of Arbitration Board No. 458 are not
applicable to the instant case. Carrier also contends that as
established by Letter 3A, the term "deliberately delayed" in
Article V, Section 1 of Arbitration Board No. 458 does not
include an inbound train that is being held to allow an outbound
train to come out of the yard or to allow another train destined
to the same yard to run around the first train.
The Board has determined that the claim must be sustained.
Initially, it must be noted that the Board has not
considered the procedural argument originally raised by carrier.
More specifically, Carrier at first argued that the Board may
not have jurisdiction to hear this case. Thereafter, without
prejudice to its position, Carrier withdrew that argument and
requested that the Board render a decision in this case on its
merits.
As to those merits, the Organization has persuasively argued
that Article R-c-2,
when viewed
within the context of Article V
of Arbitration Board No. 458, provides for payment of FTD if an
engineer is held from entering the yard by a preceding train
under circumstances such as are here present. More specifically,
the Organization has established that claimant was unable to yard
his train because he was stopped behind inbound train TTSE-8,
LDSE-7, and PYSE-7 at CP-SK. Although Carrier contends that
Claimant's train was held to allow outbound Trains TV-10 and TV8B to operate through the interlocking onto the main track, the
4
SBA AJc~ ~ E3175'- AcvO ,vo- / <//~.
Hoard finds insufficient evidence in the record developed on the
property to support this contention and Carrier's subsequent
conclusion that the claim should be denied.
Accordingly, the Board finds that the claim should be
sustained.
0
SWARD
Claim sustained. Money owed to be paid within thirty days.
R. W. Godw n, ,
Organizat' n Mem s~-- Carrier Member
S. E. Buchheit,
Neutral Member
7
~y-9.s-
s
t