BEFORE SPECIAL BOARD OF ADJUSTMENT NO. 924
BROTHERHOOD OF MAINTENANCE OF WAY EMPLOYEES
and
CHICAGO & NORTH WESTERN TRANSPORTATION COMPANY
Case No. 182
Award No.jlq~
STATEMENT OF CLAIM: Claim of the System Committee of the
Brotherhood that:
1. The five (5) day suspension assessed Common
Machine Operator R. E. Sturkol was without
just and sufficient cause and on the basis of
an unproven charge (Organization File 8KB4545D; Carrier File 81-90-41).
2. Claimant R. E. Sturkol shall be compensated
for all lost time and have the discipline
notation removed from his personal record.
FINDINGS:
On November 29, 1990, Claimant R. E. Sturkol was operating a
bulldozer on the north side of the tracks at the Pine street
bridge where a project to shift tracks was underway. While
dressing off an area where trees and brush were close to the
siding so as to allow for safe train operations, Claimant dug
four to four and a half feet and inadvertently cut a fiber optic
cable buried there.
As a result, Claimant was notified to attend a hearing on
the following charge:
Your responsibility when you were working as a machine
operator near Pine Street in Milwaukee, Wisconsin on
November 29, 1989, when you did not determine if there
were underground utilities in the area where digging
took place and fiber optic cable was cut.
As a result of this hearing, the Carrier assessed the
Claimant a five-day suspension contending that it was the
SsA 9 Zy-~w~o I
~~
sufficient evidentiary basis that he was responsible for the
accident. Therefore, the claim will be sustained.
AWARD:
Claim sustained. The five-day suspension shall be removed
from the Claimant
'(s
r~
d;,
and he shall be made whole.
PETER /R. : MEYERS
Neutr' Mem er
'Car ier Member O anization Memb
1
A&I
/.Dated:
3
SeA 9 2N - )a
wAu
I ~/
Claimant's responsibility to thoroughly and properly check for
buried cable in the area that he was digging and that the
Claimant was knowledgeable of such procedures as he had been
doing similar work all year long.
The parties being unable to resolve the issues, this matter
came before this Board.
This Board has reviewed the evidence and testimony in this
case, and we find that the Carrier has not presented sufficient
proof that the Claimant was responsible for the incident that led
to the fiber optic cable being cut. Therefore, the claim will
have to be sustained.
The record reveals that the cable that was severed was owned
by a company known as Diginet and it was not listed on the
Digger's List of cables that were buried in the area. Moreover,
the record reveals that the Claimant was not in charge of the
project, the project was already in progress and partially
completed when the Claimant arrived to begin his assignment, and
the Claimant was instructed by supervisors to perform the work in
the area where the fiber optics cable was severed.
It is fundamental that in order to assess discipline, the
Carrier must present sufficient evidence that the Claimant was
responsible for the wrongdoing. In this case, there were a
sufficient number of other people, plus a failure of the company
itself to list the cable on the hotline, which contributed to the
accident. This Board finds that it was unreasonable for the
carrier to issue a five-day suspension to the Claimant without a
2