SPECIAL BOARD OF ADJUSTMENT N0. 924
Award No. 90
Docket No. 100
PARTIES: Brotherhood of Maintenance of Way Employes
TO
DISPUTE: Chicago and North Western Transportation Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The thirty (30) day suspension assessed Track Foreman W.J.
Frasher was unwarranted, unjust and must not stand.
[Organization File 7D-5158; Carrier File 81-85-93-D]
(2) Claimant W.J. Frasher is entitled to the remedy prescribed in
Rule 19(d)."
FINDINGS:
This Board, upon the whole record and all the evidence, finds and
holds that the employees and the Carrier involved are respectively
employees and Carrier within the meaning of the Railway Labor Act as
amended and that the Board has jurisdiction over the dispute herein.
On December 11, 1984, Claimant was assisting a crane operator;
the boom of the crane struck electrical wires and damaged both the
cables and the poles. Claimant subsequently was directed to attend a
formal investigation of the charge:
Your responsibility for Ohio Crane 17-1776 knocking down of
electrical wires at M.P. 46.9 on the St. James Subdivision at
Belle Plaine, MN at approximately 9:30 A.M. on December 11, 1984
while assigned as a Track Foreman.
The investigation was held as scheduled, and a copy of the transcript
has been made a part of the record. We find that the investigation
was conducted in a fair and impartial manner.
The Organization contends that Carrier has failed to establish
Claimant's responsibility for the incident. When the incident
occurred, Claimant was flagging the road crossing; moreover, Claimant
knew that the crane operator was aware of the wires. The organization
1
asserts that Carrier has not shown that Claimant acted in an unsafe or
irresponsible manner. The organization argues that when discipline is .
excessive, arbitrary, capricious, or unwarranted, the discipline
cannot stand. The Organization therefore contends that the claim
should be sustained.
The Carrier argues that the charges against Claimant were proven,
and the assessed discipline was warranted. Carrier points out that
because the wires were knocked down, it is obvious that Claimant did
not make sure that there was adequate clearance for the crane and the
boom. Moreover, if the boom is not secured, it is possible that the
boom will bounce as the crane moves. Carrier contends that it was
reasonable for it to conclude that Claimant was negligent in the
performance of his duties. The assessed discipline was not arbitrary
or unreasonable, and the claim should be denied in its entirety.
This Board has reviewed the evidence and testimony in this case,
and we find that there is not sufficient evidence in the record to
support the finding that the Claimant was guilty of being responsible
for the crane accident. Hence, the claim should be sustained.
The record makes it clear that the Claimant was four car lengths
away from the accident when it occurred. The Claimant had observed
the crane on his way to the front car to do the flagging and did not
believe that there was any problem with the angle of the crane. The
Claimant was aware that the crane operator knew about the overhead
wires, and the Claimant went about his own business. He can hardly be
held responsible for the accident that occurred later.
2
58;4
9a-Y-~L9 g°
Award:
Ca. ier Member
1,41
Date:
Claim sustained...
'Organization Memb