SPECIAL BOARD OF ADJUSTMENT N0. 924
Award No.
91
Docket No. 109
PARTIES: Brotherhood of Maintenance of Way Employes
TO
DISPUTE: Chicago and North Western Transportation Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The thirty (30) day deferred suspension assessed Machine
Operator J.J. Mulvaney for alleged failure to operate a Little
Giant Crane in a safe manner is unjust, improper and based on an
unproven charge. [Organization File 2D-5120; Carrier File 81-8595-D]
(2) Claimant J.J. Mulvaney shall be allowed the remedy prescribed in
Rule 19(d) of the effective Agreement."
FINDINGS:
This Board, upon the whole record and all the evidence, finds and
holds that the employees and the Carrier involved are respectively
employees and Carrier within the meaning of the Railway Labor Act as
amended and that the Board has jurisdiction over the dispute herein.
On November 4, 1984, Claimant was working as a temporary Little
Giant Crane operator. While Claimant operated the crane, the boom
cable was damaged, requiring replacement. Claimant subsequently was
directed to attend a formal investigation of the charge:
Your responsibility for failure to perform your duties in a safe
manner, resulting in damage to Little Giant Crane 17-2879, while
employed on Job Number 903, Machine Operator, Des Moines, Iowa,
Shortline Yard, on November 4, 1984.
The investigation was held as scheduled, and a copy of the transcript
has been made a part of the record. We find that the investigation
was conducted in a fair and impartial manner. '
The Organization contends that Carrier has failed to meet its
burden of proof. Claimant testified that the damage occurred when the
cable popped out of the pulley groove; Carrier witnesses stated that
1
56A gay-Awo 97
the damage was caused by the improper hook-up of the magnet, but
neither of them observed the crane in operation on the day in
question. One Carrier witness stated that the bolt was missing and
might have vibrated loose after the cable was installed two days
before the day in question. The Organization asserts that, the damage
was caused by a mechanical problem; Claimant cannot be held
responsible for unforeseeable mechanical failures. The organization
therefore contends that the claim should be sustained.
The Carrier argues that the charge against Claimant was proven,
and the assessed discipline was warranted. Carrier contends that
there is substantial evidence in the record showing that Claimant was
responsible for the damage to the cable; it was reasonable for Carrier
to conclude that Claimant had failed to tie down the sheave block,
causing the.cable to. twist and rub. Carrier asserts that the missing
bolt apparently did not cause the damage. Carrier argues that under
the circumstances, the assessed discipline was neither arbitrary nor
unreasonable, and the claim should be denied in its entirety.
This Board has reviewed the evidence and testimony in this case,
and we find that there is sufficient evidence in the record to support
the finding that the Claimant was guilty of the offense with which he
was charged. The Claimant had the responsibility of operating the
crane in a safe manner. Part of that responsibility involves making
sure that the crane is operating properly before commencing an
operation. The Claimant was the crane operator and failed in his
responsibilities. Hence, he was properly found guilty.
Once this Board has determined that a claimant has been properly
found guilty of the charges against him, we next turn our attention to
the type of discipline imposed. In this case, the Claimant received a
2
5~,9
~7ay-
,9wn ~'7
30-day deferred suspension for his wrongdoing. We see
nothing
unreasonable, arbitrary, or capricious with that discipline and we
will not set it aside.
Award:
Claim denied.
/-
1
' Neutral Member
~~arrier Member 0 ganization r
J
n
Date:
AZZ
/$'d'%
3