SPECIAL ADJUSTMENT BOARD NO. 947
Claimant - S. E. Midbust
Award No. 107
Case No. 107
PARTIES Brotherhood of Maintenance of Way Employes
TO and
DISPUTE Southern Pacific Transportation Company (Western
Lines)
r
STATEMENT That the Carrier's decision to suspend
OF CLAIM Claimant for a period of three (3) days was
excessive, unduly harsh and in abuse of
discretion, and in violation of the terms and
provisions of the current Collective
Bargaining Agreement.
That because of the Carrier's failure to prove
and support the charges by introduction of
substantial bona fide evidence, that Carrier
now be required to compensate Claimant for any
and all-loss of earnings suffered, and that
the charges be removed from his record.
FINDINGS
Upon reviewing the record, as submitted, I find that the
Parties herein are Carrier and Employes within the meaning of
the Railway Labor Act, as amended, and that this Special Board
of Adjustment is duly constituted andhas jurisdiction of the
Parties and the subject matter; with this arbitrator being sole
signatory.
On January 24, 1990, near Rawson, MP 218.5, the Claimant
was driving a mobile crane which was picking up scrap behind a
tie gang. Allegedly, he failed to make sure the way was clear
1
997
- 1
c)7
upon entering a siding and the operator of the crane knocked
over a dwarf signal. The operator was offered and accepted
thirty (30) demerits and signed a waiver. The Claimant was
offered, but rejected a waiver which would have given him a
three (3) day suspension. He was susbsequently notified to
appear for a formal hearing to be held at Dunsmuir, California
on Friday, February 9, 1990, to determine whether he had
violated Rules 1.1.30 and 1.1.31 of the Chief Engineers
Instructions for the Maintenance of Way and Structures, those
portions which read:
Rule 1.1.30:
Crane Operators shall only accept signals
from those specifically designated and
authorized to give same.
They must not move loads unless they are
sure that the way is clear. Employes must
not go under load or boom except when
necessary and must be clear when load is
freed to avoid being caught between load and
other object.
Rule 1.1.31:
Employes handling or operating moving
equipment must be prepared to stop short of
persons or objects.
On the day of the incident, the Claimant was driving a
crane, while the operator of the crane was picking up scrap
around the tracks by use of a magnet attached to the end of the
boom. Near MP 218.5, they entered into a siding from the main
line. A dwarf signal was located in the siding beyond the
switch. After clearing the switch, the operator began swinging
the magnet. He was on the opposite side of the dwarf signal and
his vision was blocked by the boom. The only person who could
2
~y7-l07
see the dwarf signal was the driver, who could observe the
structure through his rear view mirror. He was also able to see
when the magnet approached the signal. Despite this, the driver
did not signal the operator to center his boom, nor did he slow
down or stop as he neared the signal. Either of the latter -
actions would have indicated to the operator that they were
approaching an obstacle. Without this indication from the
driver, the operator continued swinging the magnet and dragged
it over the dwarf signal, pulling it out of the ground. The
total cost of the damage was $4000.00.
In this matter, the Claimant would have the Board believe
he should not be held responsible because the crane operator
should have known where the dwarf signal was simply because he
had been in and out of the siding many times. However, earlier
in his testimony the Claimant explained that the direction of
travel determined who was responsible for giving instructions
and in this case it was his responsibility. Besides, unlike the
operator, the driver's vision was not hampered and he was in a
position to see ahead of time any obstacles. It was his
obligation to signal the operator. He was also able to stop the
vehicle short of the object, but chose not to do so.
The Claimant also excuses his lack of actionby contending
the operator had no reason to swing out the boom and use his
magnet since there was no scrap in the area. But, there was no
evidence presented to show an absence of scrap. And even if
there was, the Claimant testified that he was able to see the
boom of the crane. If he felt there was a problem using it in
3
~~-io7
that 'area, he had the option of slowing down or stopping.
Regardless, the absence of scrap would not excuse his failure to
signal the operator.
The Union raises the argument of disparate treatment since
the operator was offered a waiver of thirty (30) demerits, while
the Claimant was offered a waiver with a three (3) day
suspension. There are cases when disparate treatment is
sufficient cause to overturn penalties which are issued. It is
questionable here, whether the penalties issued actually
constitute disparate treatment. In the Board's view, the
Claimant was in a better position to see obstacles and was in
control of the forward motion of the vehicle. It was also a
matter of past practice that the individual in the forward
moving direction signaled the other employe of impending
hazards. The Claimant failed to do this. Based on normal
operating procedures it was his responsibility. Therefore, in
this case, assessing different penalties to the two employes
goes to who had the greater responsibility.
Finally, the Board has considered whether
or
not the.
penalty assessed to the Claimant was appropriate in view of the
rule violation and the Claimant's overall employment record.
The Claimant has been issued demerits on two other occasions for
damaging railroad property. Besides these instances, he has
been counseled concerning other rule violations. Because of
this the Board does not believe the discipline is excessive.
The Claimant was afforded a full and fair hearing. The
Carrier met its burden of proof and the penalty was reasonable.
4
AWARD
The claim is denied.
G `- a
arol J. Zamperini
Neutral
Submitted:
March 30, 1990
Denver, Colorado
5