SPECIAL BOARD OF ADJUSTMENT N0. 947
Case No. 136
Award No. 136
Claimant: David L. Gillings
PARTIES Brotherhood of Maintenance of Way Employees
TO and
DISPUTE Southern Pacific Transportation Company
9
STATEMENT 1. That the Carrier's decision to suspend
OF CLAIM Claimant David L. Gillings for a period of
sixty (60) calendar days was excessive, unduly
harsh and in abuse of discretion and in
violation of the terms and provisions of the
Collective Bargaining Agreement.
2. That because of the Carrier's failure to prove
and support the charges by introduction of
substantial bona fide evidence, that Carrier
now be required to reinstate and compensate
Claimant for any and all loss of earnings
suffered, and that the charges be removed from
his record.
FINDINGS
Upon reviewing the record, as submitted, I find that the
Parties herein are carrier and Employees within the meaning of
the Railway Labor Act, as amended, and that this Special Board of
Adjustment is duly constituted and has jurisdiction of the
Parties and the subject matter; with this arbitrator being sole
signatory. ,_
On August 24, 1992, the Carrier notified the Claimant to be
present at the office of the,District Engineer, 9499 Atkinson
Street, Roseville, California (Conference Car), at 9:00 a.m., for
a formal investigation. The purpose of the hearing was to
determine.whether the Claimant had violated the rules cited below
on August 19, 1992, when the TKO Tie Inserter Remover, he was
operating ran into two Spike Pullers at Norden, California near
MP 192.1.
qUn-i3(~'
The rules allegedly violated are:
Rule 2.13.3 Equipment shall not be operated in a manner
to endanger life, limb or property. No
equipment shall be set in motion until it is
known that the way is clear.
Rule 2.13.32 Track machines must be operated at a safe
speed at all times, subject to conditions,
especially on grades, both while working and
while running light.
Rule 2.13.34 Operators of track machines, roadway machines
or equipment are charged with the
responsibility of knowing that their machines
or equipment are in safe operative condition
before starting, and must assure themselves
that proper protection is being afforded
their operations.
The hearing was postponed until September 2, 1992.
The carrier reviewed the evidence presented at the hearing
and decided it was sufficient to find the Claimant guilty of the
rules violations. By letter dated September 16, 1992, the
Company suspended the Claimant for sixty (60) calendar days,
commencing 12:01 a.m., September 17, 1992 through 11:59 p.m.,
November 15, 1992. On October 13, 1992, the Carrier notified the
Claimant that the suspension was reduced to thirty-two (32) days,
concluding at 11:59 p.m.on Sunday, October 18, 1992.
On the morning of August 19, 1992, Rail Gang No. 5 was
scheduled to do track repair work on the No. 1 main track. They
were to wait in the clear on the turn table lead at Norden,
California at MP 192.10, and then, follow Rail Gang No. 1 onto
the main track. After the Rail Gang No. 1 began moving in an
easterly direction on the main track, two of the operators from
Rail Gang No. 5 moved their Spike Pullers into the spur. Two or
three minutes later, the Claimant moved his machine, the T.K.o.
tie inserter and remover, coupled to a tie handler, toward the
main track. He failed to see the spike pullers in time and ran
into them. One spike puller operator had jumped from his
machine, but the other did not foresee the collision and suffered
aback injury.
2
GL41-(3(,,
DECISION
There are two things, in particular, which make the
Claimant's position untenable. First of all, the two Spike
Pullers of Tie Gang No. 5 had proceeded through the spur, without
incident, and were waiting to enter the main track once it was
clear.-Secondly, there was unrefuted evidence that the sight
distance from the Spike Puller to the T.K.O., at the start of the
run was 340 feet. Tests were run the day after the accident and
it was determined that if the T.K.O. attached to the Tie Handler
had been going 4-5 mph as the crew claimed, it should have been
able to stop within twenty-eight feet after the Claimant applied
the brakes. The Claimant said he applied the brakes at the 200
foot point, therefore, he should have been able to stop
approximately 170 feet from the Spike Pullers. As revealed by
the tests, even if the T.K.O. had been traveling at a speed of 67 mph, it should have been able to stop short of the Spike
Pullers.
There is insufficient evidence to support the claimant's
contention regarding faulty brakes. Since this amounted to an
affirmative defense, the burden falls on the Claimant to provide
sufficient proof the brakes did not work properly. Furthermore,
if the lighting was as bad as the Claimant contends, he should
have proceeded at a speed which would have allowed him to stop
short of the Spike Pullers. Finally, in the tests run the day
after the accident, it became apparent that the Tie Handler which
was coupled to the T.K.O. seemed to decrease the stopping
distance required by the T.K.O. rather than increase the
acceleration.
Since the evidence indicates the Claimant was culpable in
the incident, the only remaining question is whether his record
can be used to mitigate the penalty. Even though the penalty was
reduced from a 60 calendar day suspension to a 32 calendar day
suspension, the fact remains this appears to be a substantial
penalty in view of the Claimant's record. Therefore, the Board
believes the penalty should be
reduced to
a 20 ''calendar
suspension, effective 12:01 a.m., September 17, 1992 through
11:59 p.m., October 6, 1992.
3
qq-?- i3(0
AWARD
The claim is upheld to the extent outlined above. The Claimant
is to be reimbursed for any loss of wages and benefits lost by
his suspension which exceeded twenty calendar days.
Carol J. Zamperini
Neutral
Submitted:
May 12, 1992
Denver, Colorado
4