SPECIAL BOARD OF ADJUSTMENT N0. 947
Case No. 141
Award No. 141
Claimant: L. W. Stein
PARTIES
Brotherhood of
Maintenance of Way Employees
TO and
DISPUTE Southern Pacific Transportation Company
STATEMENT 1. That the Carrier's decision to suspend
OF CLAIM Claimant from its service for a period of
five (5) days was excessive, unduly harsh and
in abuse of discretion and in violation of the
terms and provisions of the Collective
Bargaining Agreement.
2. That because of the Carrier's failure to prove
and support the charges by introduction of
substantial bona fide evidence, that Carrier
now be required to reinstate and compensate
Claimant for any and all loss of earnings
suffered, and that the charges be removed from
his record. - -
FINDINGS
Upon reviewing the record, as submitted, I find that the
Parties herein are Carrier and Employees within the meaning of
the Railway Labor Act, as amended, and that this Special Board of
Adjustment is duly constituted and has jurisdiction of the
Parties and the subject matter; with this arbitrator being sole
signatory.
After reviewing the record taken at a formal hearing held in
Tucson, Arizona, February 18,1993, the Carrier determined the
Claimant had violated Rule 965 of the Rules of the Maintenance of
Way and Structures, Southern Pacific Transportation Company, on
February 1, 1993, when he ran his Tie Crane over the east switch
at Bon, MP 908.3, at a speed in excess of extreme caution and
over 5 MPH. As a result, when 'the dispatcher attempted to
realign the switch while the machine was over the switch points,
the Tie Crane derailed and the Claimant was injured.
G~ ~ n1
The Claimant was charged with violating Rule 965, that part
which reads:
Rule 965. OPERATION OF TRACK CARS
SWITCHES:. . .Operators must use extreme caution when
running over switches. . .Reduce speed when approaching
power operated switches, and do not pass over same in
excess-of five miles per hour. . .
On the day of the incident, the Claimant was operating the
Tie Crane on Tie Gang T-8. The Gang was waiting to obtain
authority to exit the siding and enter the main track in an
easterly direction. The switch at the east end had to be aligned
before they could begin movement. Normally, the Foreman of the
Gang would have received track and time and would have thrown the
selector lever of the switch to the hand throw position. This
would have allowed the Foreman to maintain control of the switch.
However, the Foreman for some reason, left the switch in the
motor mode which allowed the dispatcher to retain control of the
switch. The crew began moving their equipment out of the siding.
The Claimant was about sixth in line. As the Claimant moved his
machine over the switch points at the east end of the siding, the
dispatcher, for whatever reason, attempted to realign the switch.
This action caused the Tie Crane, which was carrying nine ties,
to derail. The Claimant suffered injuries to his back and hip.
The organization argues that the Claimant did proceed very
cautiously over the switch. Even though he may have
"guestimated" his speed initially as between 15-20 MPH, there was
no way he had of knowing his exact speed since there is no
speedometer on his machine. In fact, there is no way any one
could tell the speed at which he was operating his machine, the
evidence against the Claimant is circumstantial. Besides, it was
not his fault the dispatcher chose this particular time to throw
the switch. If anything, the fault should lie with the
dispatcher. The Claimant has not suffered a reportable injury
during his tenure, further proof of the car-eful manner in which
he approaches his work. He even tried to avoid reporting this
accident. He worked the entire week before the pain became so
severe he had to finally report the injury.
The Carrier contends the Claimant is guilty as charged. Not
only did he tell the Roadmaster, immediately after the accident,
that he was going 15-20 MPH, but the Tie Crane traveled a
distance of 40 feet after it derailed, which clearly indicates he
was operating in excess of 5 MPH.
2
C~U~-
nl
J
DECISION
Contrary to the testimony of the Claimant, the Board
believes that a machine carrying nine ties would not have gone 40
feet after derailing, if, it was being operated at a speed of 5
MPH. Instead, it is more likely that a machine carrying that
much weight and traveling only 5 mph would have had so much
inertia it would not have traveled very far after leaving the
track. Therefore, the Board believes the carrier had sufficient
support for its contention that the Claimant was traveling at a
speed in excess of 5 MPH. The Claimant was, at least in part,
responsible for the derailment.
Even though the Claimant has a good employment record, the
Board believes the penalty issued in this case, (5 day
suspension) was reasonable under the circumstances.
AWARD
The claim is denied.
. _ t
Carol J. Zamperini
Impartial Neutral
Submitted:
July 14, 1993
Denver, Colorado
3