- L.
SPECIAL BOARD OF ADJUSTMENT NO. 947
Case No. 172
Award No. 172
Claimant: L. R. Gutierrez -
PARTIES Brotherhood of Maintenance of Way Employees -
TO and
DISPUTE Southern Pacific Lines . . _
STATEMENT 1. That the Carrier's decision.to assess
OF CLAIM Claimant a five (5) working day suspension
without pay was excessive, unduly harsh and
in abuse of discretion and in violation of
the terms and provisions of the Collective
Bargaining Agreement.
2. That becauseof the carrier's failure to
prove and support the charges by introduction
of substantial-bona fide evidence, that
Carrier now be required to reinstate and
compensate Claimant for any and all loss of
earnings suffered, and that the charges be
removed from his record.
FINDINGS
Upon reviewing the record, as submitted, I find that the
Parties herein are Carrier and Employees within the meaning of
the Railway Labor Act, as amended, and that this Special Board of
Adjustment is duly constitutedand has jurisdiction of the
Parties and the subject matter; with this arbitrator being sole
signatory.
The Claimant was a Grinder Operator on a two-man welding
crew, Welding Gang 82. Normally, he was assigned to the-Indio
District. However on August 22, 1995, he and his co-worker were
told to report to West Colton Yard where they were to grind the
stock rail switch and frogs. They met their supervisor there and
assisted in unloading a Switch Binder Model MC-3 with their Boom
Truck. After the grinder was serviced they were to proceed with
their work. It is not clear whether they started their work that
day or the next. In either case, they worked uneventfully until
August 25, 1995.
Around 11:30 orgy August 25, 1995, the Claimant testified that
they heard a train approaching the work site. They decided to
clear the track in order to allow thetrain to pass.--When they
tried to use the Boom Truck, it would not operate. With the
q~--na
train moving toward them, the crew decided to move the grinder by
hand. While doing so, the Claimant fell breaking his wrist and
injuring his back. His co-worker also slipped injuring his lower
back. An investigation was held shortly afterwards and the two
men were taken to the doctor.
On September 7, 1995, a charge letter was sent to both
employees directing them to appear at a formal investigation to
be held at the Office of the Division Engineer at Bloomington,
CA., on September 26, 1995. Since neither crew member received
the notice in a timely fashion and did not receive subsequent
notices of postponement, the Investigation was continued to
November 1, 1995. The original charge letter alleged violations
of the following Carrier Safety Rules:
Rule 1.1 Safety
Safety is the most important element in performing duties.
Obeying the rules is essential to job safety and continued
employment.
It is the responsibility of every employee to exercise care
to avoid injury to themselves or others. Working safely is
a condition of employment with the Company. The Company
will not permit any employee to take an unnecessary risk in
the performance of duty.
No job is so important, no service so urgent, that we cannot
take the time to perform all work safely.
Rule 1.1.1 Maintaining a Safe Course
in case of doubt or uncertainty, take the safe course.
Rule 1.1.2 Alert and Attentive
Employees must be careful to prevent injuring themselves or
others. They must be alert and attentive when performing
their duties and plan their work to avoid injury.
Rule 1.6 Conduct, that part reading:
Employees must not be:
1. Careless of the safety of themselves or others
2. Negligent
Any act of. . .willful disregard or negligence affecting the
interests of the Company or its employees is sufficient
cause for dismissal. . .
2
q~(~-i-a
After reviewing the evidence developed at the Investigation,
the Carrier ruled the Claimant was guilty of the charges and
issued him a five (5) day suspension without pay to be served
immediately upon his return towork from his injury leave.
The Organization, on behalf of the Claimant, contends the
Carrier has failed to meet its burdeen_ of_ proof.__ -They also-point
out that no one can be blamed for equipment failure and there was
no doubt that the Boom Truck for some unknown reason failed to
operate when the two men attempted to clear the Grinder from the
track.
Furthermore, they point out that the crew had never worked
in the West Colton Yards and fully believed they were responsible
for removing the Grinder from the track when
a
train approached.
They did not believe trains would stop and seek their permission
before proceeding across the switch and out of theyard.
Therefore, when the Boom Truck failed, they saw no alternative
than to manually remove the Grinder.
Finally, the Organization proffers the Claimant's years of
experience as a mitigating factor-They
suggest,
ifanything, it
was a lack of communication which caused the ,Claimant and his co
worker to believe it was necessary to-manually remove the grinder
from the track, it was not an intentional disregard for the
supervisor's instructions. Therefore,the Carrier should merely -
issue the Claimant a slap on the wrist for
his
actions. _
The Carrier argues that the Claimant's-supervisor, on
several occasions, made it clear the Boom T.ruck._was to be used - _
any time the Grinder had to be moved. Furthermore, the crew had
personally cleared track and time within the
West
Colton Yard ,_
when they were making the repairs to the switcl~..~They should
have been aware that trains would stop short of their work site
and seek permission before proceeding.- In any case, when the
crew realized the Boom Truck was not working, they could have
flagged the train if they did not believe it would have stopped
on its own.
The Board has reviewed the case carefully. The Board does
not believe the Claimant intentionally ignored the supervisor's
directive not to remove the grinder-by hand. -His failure to
comply with the direct order was more a response to the equipment
failure. Regardless, he did violate clear instrilctions.____. _ ____
Furthermore, as pointed out at hearing and is evident from the
Claimant's employment record, he has been employed with the
Carrier for over 17 years. It ishard for this Board to believe
the Claimant did not know that once the crew obtained track and
time, trains had to wait for their clearance before proceeding
over the switch. Besides, the Carrier correctly asserts that if
the Claimant truly believed the train would automatically proceed
3
qY~ i ~a
through the switch, he had the prerogative to red flag the train
once he realized the Boom Truck did not work.
Finally, the Claimant's testimony was inconsistent at times.
The Board does not believe he was as forthcoming as he should
have been. In contrast, the testimony of the supervisor was
credible.
For all of these reasons, this Board believes the Carrier
has met its burden of proof and the penalty issued was
appropriate.
AWARD
The claim is denied.
L
Carol J. Zamperini, Neutral
Submitted:
March 29, 1996
Denver, Colorado
4