SPECIAL BOARD OF ADJUSTMENT NO. 956
BROTHERHOOD OF MAINTENANCE }
OF WAY EMPLOYEES }
and } AWARD NO. 147
} CASE NO. 147
NEW JERSEY TRANSIT RAIL }
OPERATIONS, INC. }
STATEMENT OF CLAIM:
Claim on behalf of R. Carbone, Class H Operator, for expungement of discipline
assessed, payment for all time lost, and reimbursement for benefits lost during time
withheld from service.
FINDINGS:
Special Board of Adjustment No. 956, upon the whole record and all the
evidence, finds that the parties herein are Carrier and Employes within the meaning
of the Railway Labor Act; as amended; that the Board has jurisdiction over the
dispute herein; and that the parties to the dispute were given due notice of the
hearing and did participate therein.
On November 4, 2003, the Claimant was assigned as a Production Gang
Foreman. At approximately 7:15 p.m., he was working with the on-track Lag
Machine NL202, which was being operated by Class II Equipment Operator A.
Baroni. After fmishing one section of the out of service track, the Lag machine
proceeded east to the next work location. The conditions were dark and rainy.
Traveling around a curve, the Lag machine collided with one of two welding trucks
stopped on the tracks ahead, resulting in damage to the equipment.
The Carrier charged the Claimant with failing to identify and communicate
to the operator of the Lag machine that the speed of the equipment would not
permit stopping within half their range of vision or short of other equipment
occupying the track. After several postponements, a hearing took place on March
23, 2005. Following the hearing, the Claimant was assessed a five day suspension.
The basis for the Organization's appeal is that the discipline lacked
sufficient cause. The Organization argues that there were several factors that should
have been taken into consideration by the Carrier. Specifically, the Organization
points out that the Claimant was not informed that there was other equipment left
out on the track; the documentation known as "Form D" was not furnished to the
Claimant. In addition, the Organization asserts that the weather was inclement and
the equipment was being operated in a reverse position. Moreover, there was such
minimal damage to the equipment that the matter was not investigated until the
SBA No. 956 Award No. 147
Page 2 Case No. 147
next morning. These factors suggest to the Organization that the discipline imposed
was excessive and unwarranted. In the view of the Organization, therefore, the
claim should be sustained.
Carrier contends that the charges were proven and the discipline was
appropriate based on the nature of the misconduct. Carrier rejects the
Organization's assertion that mitigating or extenuating circumstances should
reduce the penalty imposed. The claim, therefore must be denied.
After careful consideration, the Board finds that there is substantial evidence
to support the charges directed against the Claimant. Track Supervisor Felice
explained the Claimant's role in the incident as follows:
As a foreman, he should realize the speed you are going with the conditions,
letting the operator know if he is going too fast, to make sure you slow down.
He is in charge of that machine, as is the operator, to make sure he can see at
the range of vision and be able to stop at a reasonable time and distance.
Claimant was subject to NORAC Operating Rule 80, which pertains to
movement at restricted speed. Pursuant to that rule, he was required to make sure
that the movement was controlled so as to permit stopping within one half the range
of vision short of other railroad equipment occupying the track. The record shows
that the Claimant failed to adhere to this important safety rule.
The Organization's principal argument is that there were extenuating
circumstances on the date of the incident that should have been taken into
consideration in the assessment of discipline. In the Board's view, the circumstances
relied upon by the Organization require a different conclusion. Even in inclement
weather, and regardless of whether there is prior notice of equipment ahead on the
track, it was the Claimant's responsibility to be vigilant, to make sure that the Lag
machine maintained a controlled movement to be able to stop safely. Moreover, the
record shows that it was not unusual to operate the Lag machine in reverse on the
tracks. The Organization's asserted defenses merely highlight the necessity for
adhering to the safety rules, something Claimant failed to do in this instance.
The Organization's remaining arguments are similarly without merit. The
record shows that the equipment had permission to occupy the tracks so a Form D
was not required. In addition, the fact that the Carrier waited until morning to
investigate the incident does not change the result or shift responsibility for the
collision to the Carrier. The Claimant's failure to remain alert on the date of the
incident resulted in a breach of the Carrier's safety rules. We must conclude that
the 5-day suspension under these circumstances was within the range of
reasonableness properly afforded to the Carrier in the exercise of its discretion.
SBA No. 956
Page 3
Claim denied.
Jl
Carrier Member
Agnes Duncan
Dated this '"'day of
Award No. 247
Case No. 247
AWARD
ANN S. IENIS
Neutral Member
L~I-jl
Organization Me er
William Capik